Klafastaðir, Substation on Grundartangi

The construction of a new substation at Klafastaðir, which should equalize the potential difference and in that way, increase the quality of electricity in the industrial area on Grundartangi.

VSO’s role in the project is:

  • Construction supervision for the transportation of water utility, earthwork and the construction of the substation.
  • Safety supervision during project period.

Project period: 2012-2013.

Client: Landsnet.